HOBE Energy Completes Grid Connection at Sanga Storage Station in Fukaya

Each of the five JESDI sites reached grid connection within six months of construction start, which is the evidence HOBE cites that its standardized, space-saving package can be repeated across differing site conditions.

Reporting from 1 source: ASCII.jp.

HOBE Energy Completes Grid Connection at Sanga Storage Station in Fukaya

HOBE ENERGY supplied a 5MWh-class integrated storage system for a project developed by Japan Energy Storage Development Institute in Fukaya City, Saitama Prefecture. Grid connection was completed on September 11, 2026, roughly four months after construction began. The site is JESDI's fifth grid-connected station in Japan and fourth in Saitama Prefecture, following Aisho Town and three other Saitama sites.

The Sanga Storage Station uses a 5ft compact enclosure rather than the 20ft containers described as the mainstream, a design HOBE says allows installation near homes through a layout that reduces visual pressure. The supplied package covers the system, EMS, PCS, and power receiving and transforming equipment. HOBE and JESDI have now worked together on five sites across Shiga and Saitama prefectures. The company says it will keep supplying design through power receiving equipment for JESDI projects elsewhere in Japan.

Synthesized by Yomimono from the 1 cited source below, including Japanese-language reporting where cited, then editorially reviewed before publishing.